When can I begin recording lots?

Lots can be recorded and sold once a final plat has been recorded. A final plat can be recorded: (A) once improvements are completed or improvements have been guaranteed (See Improvement Guarantee Application); or (B) where no new right-of-way is proposed and no other improvement is necessary.

Prior to recording the plat the the applicant must submit the following:

  1. Final Plat (which meets the requirements of LDC Article XI, §200A-343 (B)) prepared by a registered land surveyor (one (1) mylar and one (1) blue line copy))
  2. Fee (See Fee Schedule)

The Subdivision Administrator can approve the major subdivision final plat (provided that, if a new right-of-way was proposed, the road passes inspection or has been guaranteed (See Improvement Guarantee Application)). The signed plat must then be recorded at the Register of Deeds Office.